Solar plant: site data

Solar power plant in Ternivshchyna, Lubenskyi Raion, Poltava Oblast

Ternivshchyna: 1,128 kWh per kWp a year, tilt 37° 2° east of south (PVGIS). 1.2% below the oblast median (1,142). #276 of 346 in the rayon, #1612 of 1856 in the oblast.

Lubny, the rayon centre, is 12 km away. 103 m above sea level. 12 km away: Lubny, the nearest bigger centre, 1,146 — 1.6% less here. Snow and wind from the nearest regional centre in the DBN — Черкаси, 98 km. 12.06 m between rows, pitch 15.88 m (latitude 50.0°).

Yield of 1 kWp
1,128kWh/year
Tilt
37°2° east of south
10 kW
11,275kWh/year
Row pitch
15.88m · GCR 0.30
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,520 / 420Pa

Ground frame designer

A ground frame for a solar plant: Ternivshchyna

The designer opens with this place’s coordinates, latitude 50.0° for the row spacing and the DBN loads of the nearest regional centre — Черкаси, 98 km: snow 1,520 Pa, wind 420 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

34Jan54Feb90Mar118Apr139May143Jun147Jul145Aug114Sep82Oct37Nov24Dec

July: 147 kWh/kWp, December: 24 — 6.1 times less.

November: 37 against 39 in the oblast, 5.1% less.

Ternivshchyna: plants, kWh
kWpA yearJulyDecember
55,638735120
1011,2751,470240
1516,9132,205360

Snow and wind: Черкаси

Example: a 10 kW ground frame

For the loads of Cherkasy: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 49,705 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Lubenskyi RaionPoltava Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.