Solar plant: site data

Solar power plant in Pylypenky, Myrhorodskyi Raion, Poltava Oblast

Pylypenky: 1,150 kWh per kWp a year, tilt 37° 2° east of south (PVGIS). 0.7% above the oblast median (1,142). #11 of 430 in the rayon, #536 of 1856 in the oblast.

Myrhorod, the rayon centre, is 29 km away. 136 m above sea level. 9 km away: Velyka Bahachka, the nearest bigger centre, 1,144 — 0.5% more here. Snow and wind from the nearest regional centre in the DBN — Полтава, 61 km. 11.83 m between rows, pitch 15.65 m (latitude 49.7°).

Yield of 1 kWp
1,150kWh/year
Tilt
37°2° east of south
10 kW
11,498kWh/year
Row pitch
15.65m · GCR 0.31
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,450 / 470Pa

Ground frame designer

A ground frame for a solar plant: Pylypenky

The designer opens with this place’s coordinates, latitude 49.7° for the row spacing and the DBN loads of the nearest regional centre — Полтава, 61 km: snow 1,450 Pa, wind 470 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

38Jan58Feb96Mar118Apr139May143Jun146Jul145Aug116Sep84Oct40Nov27Dec

July: 146 kWh/kWp, December: 27 — 5.4 times less.

January: 38 against 35 in the oblast, 8.6% more.

Pylypenky: plants, kWh
kWpA yearJulyDecember
55,749730135
1011,4981,460270
1517,2472,190405

Snow and wind: Полтава

Example: a 10 kW ground frame

For the loads of Poltava: 11.16 kWp, 18 panels, 389 kg of steel, 12 piles, materials ≈ 52,358 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Myrhorodskyi RaionPoltava Oblast: rayons and towns

Free calculators

Sources