Solar plant: site data

Solar power plant in Panchenky, Myrhorodskyi Raion, Poltava Oblast

Panchenky: 1,130 kWh per kWp a year, tilt 37° 1° east of south (PVGIS). 1.1% below the oblast median (1,142). #253 of 430 in the rayon, #1520 of 1856 in the oblast.

Myrhorod, the rayon centre, is 33 km away. 140 m above sea level. 28 km away: Hadyach, the nearest bigger centre, 1,120 — 0.9% more here. Snow and wind from the nearest regional centre in the DBN — Полтава, 99 km. 12.33 m between rows, pitch 16.15 m (latitude 50.3°).

Yield of 1 kWp
1,130kWh/year
Tilt
37°1° east of south
10 kW
11,297kWh/year
Row pitch
16.15m · GCR 0.30
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,450 / 470Pa

Ground frame designer

A ground frame for a solar plant: Panchenky

The designer opens with this place’s coordinates, latitude 50.3° for the row spacing and the DBN loads of the nearest regional centre — Полтава, 99 km: snow 1,450 Pa, wind 470 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

34Jan58Feb95Mar118Apr139May143Jun146Jul145Aug112Sep80Oct36Nov24Dec

July: 146 kWh/kWp, December: 24 — 6.1 times less.

November: 36 against 39 in the oblast, 7.7% less.

Panchenky: plants, kWh
kWpA yearJulyDecember
55,649730120
1011,2971,460240
1516,9462,190360

Snow and wind: Полтава

Example: a 10 kW ground frame

For the loads of Poltava: 11.16 kWp, 18 panels, 389 kg of steel, 12 piles, materials ≈ 52,358 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Myrhorodskyi RaionPoltava Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.