Poland: solar plant site data

Solar power plant in Warsaw, Poland: yield, tilt angle and row spacing

Warsaw: 1,053 kWh per kWp a year at the optimal tilt of 39°, 3° east of south (PVGIS). 1.2% below the median of the main cities of Poland (1,065). #67 of 87 main cities of Poland by yield. For comparison, Kyiv: 1,114 kWh/kWp — 5.5% less here.

Warsaw is in Masovian Voivodeship. Population 1,702,139 (GeoNames). 113 m above sea level. 15.24 m between rows, pitch 18.96 m, GCR 0.25 (latitude 52.2°).

Yield of 1 kWp
1,053kWh/year
Tilt
39°3° east of south
10 kW
10,526kWh/year
Row pitch
18.96m · GCR 0.25
Rank in the country
67of 87 cities

Ground frame designer

A ground frame for a solar plant: Warsaw

Latitude 52.2°: the tilt and the row pitch follow it. Enter the snow and wind for Poland in the designer, by the national annex to the Eurocode.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

34Jan51Feb90Mar119Apr130May133Jun131Jul125Aug105Sep73Oct34Nov26Dec

June: 133 kWh/kWp, December: 26 — 5.1 times less.

December: 26 against the median of 32 for the main cities of Poland, 18.8% less.

Warsaw: plants, kWh
kWpA yearJuneDecember
55,263665130
1010,5261,330260
1515,7891,995390

Fixed tilt facing south

What a table yields at another tilt than the optimal 39° — for roofs and frames with a standard slope.

Warsaw: yield at a fixed tilt, kWh/kWp
TiltA yearAgainst the optimum
39° (optimum)1,053—
15°984−6.5%
30°1,042−1.0%
45°1,048−0.4%
90°749−28.8%

Snow and wind loads

Snow and wind loads for a site in Poland follow PN-EN 1991-1-3 (snow) and PN-EN 1991-1-4 (wind) with the Polish National Annex (NA). Solispec computes loads by the Ukrainian DBN V.1.2-2 only, so this page shows no snow or wind values for Poland: enter the characteristic values from these documents in the designer’s «Own snow S0» and «Own wind W0» fields.

The frame calculation for such a site is preliminary: before installation it must be checked by an engineer who works to the country’s standards.

Nearby cities

Poland: all cities and regions

Sources

Preliminary calculation: a design needs an engineer’s check.