Solar plant: site data

Solar power plant in Novosevastopol, Bashtanskyi Raion, Mykolaiv Oblast

Novosevastopol: 1,203 kWh per kWp a year, tilt 36° 3° east of south (PVGIS). Exactly the oblast median (1,198). #119 of 279 in the rayon, #387 of 909 in the oblast.

Novyi Buh, the rayon centre, is 35 km away. 78 m above sea level. 14 km away: Bereznehuvate, the nearest bigger centre, 1,216 — 1.1% less here. Snow and wind from the nearest regional centre in the DBN — Миколаїв, 75 km. 9.82 m between rows, pitch 13.69 m (latitude 47.4°).

Yield of 1 kWp
1,203kWh/year
Tilt
36°3° east of south
10 kW
12,032kWh/year
Row pitch
13.69m · GCR 0.35
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
870 / 470Pa

Ground frame designer

A ground frame for a solar plant: Novosevastopol

The designer opens with this place’s coordinates, latitude 47.4° for the row spacing and the DBN loads of the nearest regional centre — Миколаїв, 75 km: snow 870 Pa, wind 470 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

37Jan55Feb99Mar123Apr140May142Jun152Jul151Aug127Sep96Oct49Nov33Dec

July: 152 kWh/kWp, December: 33 — 4.6 times less.

January: 37 against 38 in the oblast, 2.6% less.

Novosevastopol: plants, kWh
kWpA yearJulyDecember
56,016760165
1012,0321,520330
1518,0482,280495

Snow and wind: Миколаїв

Example: a 10 kW ground frame

For the loads of Mykolaiv: 11.16 kWp, 18 panels, 372 kg of steel, 14 piles, materials ≈ 50,842 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Bashtanskyi RaionMykolaiv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.