Solar plant: site data

Solar power plant in Novoochakiv, Bashtanskyi Raion, Mykolaiv Oblast

Novoochakiv: 1,200 kWh per kWp a year, tilt 36° 3° east of south (PVGIS). Exactly the oblast median (1,198). #134 of 279 in the rayon, #427 of 909 in the oblast.

Novyi Buh, the rayon centre, is 31 km away. 82 m above sea level. 22 km away: Bereznehuvate, the nearest bigger centre, 1,216 — 1.3% less here. Snow and wind from the nearest regional centre in the DBN — Миколаїв, 86 km. 9.88 m between rows, pitch 13.75 m (latitude 47.5°).

Yield of 1 kWp
1,200kWh/year
Tilt
36°3° east of south
10 kW
11,999kWh/year
Row pitch
13.75m · GCR 0.35
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
870 / 470Pa

Ground frame designer

A ground frame for a solar plant: Novoochakiv

The designer opens with this place’s coordinates, latitude 47.5° for the row spacing and the DBN loads of the nearest regional centre — Миколаїв, 86 km: snow 870 Pa, wind 470 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

37Jan56Feb98Mar123Apr139May142Jun153Jul151Aug126Sep95Oct48Nov33Dec

July: 153 kWh/kWp, December: 33 — 4.6 times less.

February: 56 against 54 in the oblast, 3.7% more.

Novoochakiv: plants, kWh
kWpA yearJulyDecember
56,000765165
1011,9991,530330
1517,9992,295495

Snow and wind: Миколаїв

Example: a 10 kW ground frame

For the loads of Mykolaiv: 11.16 kWp, 18 panels, 372 kg of steel, 14 piles, materials ≈ 50,842 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Bashtanskyi RaionMykolaiv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.