Solar plant: site data
Solar power plant in Kryve Ozero, Pervomaiskyi Raion, Mykolaiv Oblast
Kryve Ozero: 1,169 kWh per kWp a year, tilt 36° 3° east of south (PVGIS). 2.4% below the oblast median (1,198). #88 of 140 in the rayon, #841 of 909 in the oblast.
Pervomaysk, the rayon centre, is 39 km away. 96 m above sea level. 39 km away: Pervomaysk, the nearest bigger centre, the same 1,169. Snow and wind from the nearest regional centre in the DBN — Кропивницький, 156 km. 10.17 m between rows, pitch 14.04 m (latitude 47.9°).
- Yield of 1 kWp
- 1,169kWh/year
- Tilt
- 36°3° east of south
- 10 kW
- 11,694kWh/year
- Row pitch
- 14.04m · GCR 0.34
- T_min
- -42 °Cregion II, south-eastern
- Snow S₀ / wind W₀
- 1,230 / 410Pa
Ground frame designer
A ground frame for a solar plant: Kryve Ozero
The designer opens with this place’s coordinates, latitude 47.9° for the row spacing and the DBN loads of the nearest regional centre — Кропивницький, 156 km: snow 1,230 Pa, wind 410 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 150 kWh/kWp, December: 32 — 4.7 times less.
November: 43 against 48 in the oblast, 10.4% less.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,847 | 750 | 160 |
| 10 | 11,694 | 1,500 | 320 |
| 15 | 17,541 | 2,250 | 480 |
Example: a 10 kW ground frame
For the loads of Kropyvnytskyi: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 48,082 UAH.
How these numbers are computed
Nearby
- Kryve Ozero Druhe2 km1,177 kWh/kWp
- Aheivka6 km1,174 kWh/kWp
- Mazurove7 km1,173 kWh/kWp
- Antonivka7 km1,171 kWh/kWp
- Yanyshivka8 km1,173 kWh/kWp
- Burylove8 km1,166 kWh/kWp
All places: Pervomaiskyi RaionMykolaiv Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.