Solar plant: site data

Solar power plant in Krasnopil, Pervomaiskyi Raion, Mykolaiv Oblast

Krasnopil: 1,178 kWh per kWp a year, tilt 35° 6° east of south (PVGIS). 1.7% below the oblast median (1,198). #41 of 140 in the rayon, #739 of 909 in the oblast.

Pervomaysk, the rayon centre, is 45 km away. 82 m above sea level. 45 km away: Pervomaysk, the nearest bigger centre, 1,169 — 0.8% more here. Snow and wind from the nearest regional centre in the DBN — Одеса, 143 km. 9.79 m between rows, pitch 13.71 m (latitude 47.7°).

Yield of 1 kWp
1,178kWh/year
Tilt
35°6° east of south
10 kW
11,778kWh/year
Row pitch
13.71m · GCR 0.35
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
880 / 460Pa

Ground frame designer

A ground frame for a solar plant: Krasnopil

The designer opens with this place’s coordinates, latitude 47.7° for the row spacing and the DBN loads of the nearest regional centre — Одеса, 143 km: snow 880 Pa, wind 460 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

37Jan51Feb97Mar122Apr140May142Jun151Jul147Aug121Sep93Oct45Nov33Dec

July: 151 kWh/kWp, December: 33 — 4.6 times less.

November: 45 against 48 in the oblast, 6.3% less.

Krasnopil: plants, kWh
kWpA yearJulyDecember
55,889755165
1011,7781,510330
1517,6672,265495

Snow and wind: Одеса

Example: a 10 kW ground frame

For the loads of Odesa: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Pervomaiskyi RaionMykolaiv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.