Solar plant: site data

Solar power plant in Zagorody, Yavorivskyi Raion, Lviv Oblast

Zagorody: 1,082 kWh per kWp a year, tilt 38° 1° west of south (PVGIS). Exactly the oblast median (1,084). #63 of 148 in the rayon, #865 of 1532 in the oblast.

Yavoriv, the rayon centre, is 19 km away. 222 m above sea level. 19 km away: Yavoriv, the nearest bigger centre, the same 1,085. Snow and wind from the nearest regional centre in the DBN — Львів, 48 km. 12.14 m between rows, pitch 15.91 m (latitude 49.8°).

Yield of 1 kWp
1,082kWh/year
Tilt
38°1° west of south
10 kW
10,820kWh/year
Row pitch
15.91m · GCR 0.30
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,310 / 520Pa

Ground frame designer

A ground frame for a solar plant: Zagorody

The designer opens with this place’s coordinates, latitude 49.8° for the row spacing and the DBN loads of the nearest regional centre — Львів, 48 km: snow 1,310 Pa, wind 520 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

38Jan55Feb94Mar114Apr125May127Jun132Jul131Aug107Sep82Oct44Nov32Dec

July: 132 kWh/kWp, December: 32 — 4.1 times less.

January: 38 against 39 in the oblast, 2.6% less.

Zagorody: plants, kWh
kWpA yearJulyDecember
55,410660160
1010,8201,320320
1516,2301,980480

Snow and wind: Львів

Example: a 10 kW ground frame

For the loads of Lviv: 11.16 kWp, 18 panels, 376 kg of steel, 12 piles, materials ≈ 50,491 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Yavorivskyi RaionLviv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.