Solar plant: site data

Solar power plant in Yarushychi, Stryiskyi Raion, Lviv Oblast

Yarushychi: 1,085 kWh per kWp a year, tilt 38° 2° west of south (PVGIS). Exactly the oblast median (1,084). #173 of 286 in the rayon, #720 of 1532 in the oblast.

Stryi, the rayon centre, is 8 km away. 289 m above sea level. 8 km away: Stryi, the nearest bigger centre, the same 1,085. Snow and wind from the nearest regional centre in the DBN — Івано-Франківськ, 66 km. 11.68 m between rows, pitch 15.45 m (latitude 49.2°).

Yield of 1 kWp
1,085kWh/year
Tilt
38°2° west of south
10 kW
10,847kWh/year
Row pitch
15.45m · GCR 0.31
T_min
-38 °Cregion IIIA, Carpathian
Snow S₀ / wind W₀
1,410 / 500Pa

Ground frame designer

A ground frame for a solar plant: Yarushychi

The designer opens with this place’s coordinates, latitude 49.2° for the row spacing and the DBN loads of the nearest regional centre — Івано-Франківськ, 66 km: snow 1,410 Pa, wind 500 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

41Jan57Feb91Mar113Apr122May124Jun132Jul130Aug108Sep85Oct47Nov35Dec

July: 132 kWh/kWp, December: 35 — 3.8 times less.

December: 35 against 32 in the oblast, 9.4% more.

Yarushychi: plants, kWh
kWpA yearJulyDecember
55,424660175
1010,8471,320350
1516,2711,980525

Snow and wind: Івано-Франківськ

Example: a 10 kW ground frame

For the loads of Ivano-Frankivsk: 11.16 kWp, 18 panels, 410 kg of steel, 16 piles, materials ≈ 54,212 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Stryiskyi RaionLviv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.