Solar plant: site data

Solar power plant in Trushevychi, Sambirskyi Raion, Lviv Oblast

Trushevychi: 1,082 kWh per kWp a year, tilt 39° 2° east of south (PVGIS). Exactly the oblast median (1,084). #37 of 264 in the rayon, #886 of 1532 in the oblast.

Sambir, the rayon centre, is 33 km away. 243 m above sea level. 33 km away: Sambir, the nearest bigger centre, 1,074 — 0.7% more here. Snow and wind from the nearest regional centre in the DBN — Львів, 93 km. 12.29 m between rows, pitch 16.01 m (latitude 49.6°).

Yield of 1 kWp
1,082kWh/year
Tilt
39°2° east of south
10 kW
10,815kWh/year
Row pitch
16.01m · GCR 0.30
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,310 / 520Pa

Ground frame designer

A ground frame for a solar plant: Trushevychi

The designer opens with this place’s coordinates, latitude 49.6° for the row spacing and the DBN loads of the nearest regional centre — Львів, 93 km: snow 1,310 Pa, wind 520 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

42Jan59Feb93Mar112Apr119May122Jun130Jul127Aug107Sep84Oct50Nov36Dec

July: 130 kWh/kWp, December: 36 — 3.6 times less.

November: 50 against 44 in the oblast, 13.6% more.

Trushevychi: plants, kWh
kWpA yearJulyDecember
55,408650180
1010,8151,300360
1516,2231,950540

Snow and wind: Львів

Example: a 10 kW ground frame

For the loads of Lviv: 11.16 kWp, 18 panels, 376 kg of steel, 12 piles, materials ≈ 50,491 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Sambirskyi RaionLviv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.