Solar plant: site data

Solar power plant in Sholomenitse, Lvivskyi Raion, Lviv Oblast

Sholomenitse: 1,075 kWh per kWp a year, tilt 38° facing south (PVGIS). 0.8% below the oblast median (1,084). #343 of 356 in the rayon, #1195 of 1532 in the oblast.

Lviv, the rayon centre, is 38 km away. 256 m above sea level. 26 km away: Yavoriv, the nearest bigger centre, 1,085 — 0.9% less here. Snow and wind from the nearest regional centre in the DBN — Львів, 38 km. 12.11 m between rows, pitch 15.88 m (latitude 49.7°).

Yield of 1 kWp
1,075kWh/year
Tilt
38°facing south
10 kW
10,747kWh/year
Row pitch
15.88m · GCR 0.30
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,310 / 520Pa

Ground frame designer

A ground frame for a solar plant: Sholomenitse

The designer opens with this place’s coordinates, latitude 49.7° for the row spacing and the DBN loads of the nearest regional centre — Львів, 38 km: snow 1,310 Pa, wind 520 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

34Jan50Feb94Mar115Apr125May128Jun133Jul132Aug108Sep83Oct43Nov29Dec

July: 133 kWh/kWp, December: 29 — 4.6 times less.

January: 34 against 39 in the oblast, 12.8% less.

Sholomenitse: plants, kWh
kWpA yearJulyDecember
55,374665145
1010,7471,330290
1516,1211,995435

Snow and wind: Львів

Example: a 10 kW ground frame

For the loads of Lviv: 11.16 kWp, 18 panels, 376 kg of steel, 12 piles, materials ≈ 50,491 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Lvivskyi RaionLviv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.