Solar plant: site data

Solar power plant in Horodovychi, Sambirskyi Raion, Lviv Oblast

Horodovychi: 1,080 kWh per kWp a year, tilt 39° 2° east of south (PVGIS). Exactly the oblast median (1,084). #55 of 264 in the rayon, #957 of 1532 in the oblast.

Sambir, the rayon centre, is 20 km away. 325 m above sea level. 20 km away: Sambir, the nearest bigger centre, 1,074 — 0.6% more here. Snow and wind from the nearest regional centre in the DBN — Львів, 87 km. 12.20 m between rows, pitch 15.92 m (latitude 49.5°).

Yield of 1 kWp
1,080kWh/year
Tilt
39°2° east of south
10 kW
10,800kWh/year
Row pitch
15.92m · GCR 0.30
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,310 / 520Pa

Ground frame designer

A ground frame for a solar plant: Horodovychi

The designer opens with this place’s coordinates, latitude 49.5° for the row spacing and the DBN loads of the nearest regional centre — Львів, 87 km: snow 1,310 Pa, wind 520 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

43Jan59Feb94Mar111Apr118May121Jun129Jul127Aug106Sep84Oct51Nov37Dec

July: 129 kWh/kWp, December: 37 — 3.5 times less.

November: 51 against 44 in the oblast, 15.9% more.

Horodovychi: plants, kWh
kWpA yearJulyDecember
55,400645185
1010,8001,290370
1516,2001,935555

Snow and wind: Львів

Example: a 10 kW ground frame

For the loads of Lviv: 11.16 kWp, 18 panels, 376 kg of steel, 12 piles, materials ≈ 50,491 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Sambirskyi RaionLviv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.