Solar power plant in Borynia, Sambirskyi Raion, Lviv Oblast

Borynia: 1,045 kWh per kWp a year, tilt 39° facing south (PVGIS). 3.6% below the oblast median (1,084). #185 of 264 in the rayon, #1387 of 1532 in the oblast.

Sambir, the rayon centre, is 52 km away. 608 m above sea level — above 500 m the DBN snow and wind are higher. 48 km away: Drohobych, the nearest bigger centre, 1,073 — 2.7% less here. Snow and wind from the nearest regional centre in the DBN — Ужгород, 72 km. 11.78 m between rows, pitch 15.50 m (latitude 49.1°).

Yield of 1 kWp
1,045kWh/year
Tilt
39°facing south
10 kW
10,447kWh/year
Row pitch
15.50m · GCR 0.31
T_min
-38 °Cregion IIIA, Carpathian
Snow S₀ / wind W₀
1,340 / 370Pa

Ground frame designer

A ground frame for a solar plant: Borynia

The designer opens with this place’s coordinates, latitude 49.1° for the row spacing and the DBN loads of the nearest regional centre — Ужгород, 72 km: snow 1,340 Pa, wind 370 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

43Jan59Feb89Mar108Apr114May118Jun125Jul126Aug103Sep82Oct48Nov30Dec

August: 126 kWh/kWp, December: 30 — 4.2 times less.

January: 43 against 39 in the oblast, 10.3% more.

Borynia: plants, kWh
kWpA yearAugustDecember
55,224630150
1010,4471,260300
1515,6711,890450

Snow and wind: Ужгород

Example: a 10 kW ground frame

For the loads of Uzhhorod: 11.16 kWp, 18 panels, 366 kg of steel, 12 piles, materials ≈ 48,597 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Sambirskyi RaionLviv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.