Solar plant: site data

Solar power plant in Zolote, Siverskodonetskyi Raion, Luhansk Oblast

Zolote: 1,154 kWh per kWp a year, tilt 36° 1° east of south (PVGIS). Exactly the oblast median (1,150). #26 of 100 in the rayon, #314 of 964 in the oblast.

Siverskodonetsk, the rayon centre, is 28 km away. 167 m above sea level. 28 km away: Siverskodonetsk, the nearest bigger centre, the same 1,150. Snow and wind from the nearest regional centre in the DBN — Харків, 219 km. 10.72 m between rows, pitch 14.59 m (latitude 48.7°).

Yield of 1 kWp
1,154kWh/year
Tilt
36°1° east of south
10 kW
11,536kWh/year
Row pitch
14.59m · GCR 0.33
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
1,600 / 430Pa

Ground frame designer

A ground frame for a solar plant: Zolote

The designer opens with this place’s coordinates, latitude 48.7° for the row spacing and the DBN loads of the nearest regional centre — Харків, 219 km: snow 1,600 Pa, wind 430 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

39Jan60Feb92Mar114Apr137May143Jun145Jul147Aug121Sep85Oct44Nov27Dec

August: 147 kWh/kWp, December: 27 — 5.4 times less.

February: 60 against 56 in the oblast, 7.1% more.

Zolote: plants, kWh
kWpA yearAugustDecember
55,768735135
1011,5361,470270
1517,3042,205405

Snow and wind: Харків

Example: a 10 kW ground frame

For the loads of Kharkiv: 11.16 kWp, 18 panels, 359 kg of steel, 12 piles, materials ≈ 53,991 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Siverskodonetskyi RaionLuhansk Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.