Kindrativka: 1,143 kWh per kWp a year, tilt 36° 3° east of south (PVGIS). 1.2% below the oblast median (1,157). #162 of 171 in the rayon, #672 of 708 in the oblast.
Hayvoron, the rayon centre, is 92 km away. 145 m above sea level. 14 km away: Novoarkhanhelsk, the nearest bigger centre, the same 1,148. Snow and wind from the nearest regional centre in the DBN — Кропивницький, 96 km. 10.73 m between rows, pitch 14.60 m (latitude 48.7°).
- Yield of 1 kWp
- 1,143kWh/year
- Tilt
- 36°3° east of south
- 10 kW
- 11,433kWh/year
- Row pitch
- 14.60m · GCR 0.33
- T_min
- -40 °Cregion I, north-western
- Snow S₀ / wind W₀
- 1,230 / 410Pa
Ground frame designer
A ground frame for a solar plant: Kindrativka
The designer opens with this place’s coordinates, latitude 48.7° for the row spacing and the DBN loads of the nearest regional centre — Кропивницький, 96 km: snow 1,230 Pa, wind 410 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 149 kWh/kWp, December: 28 — 5.3 times less.
January: 33 against 35 in the oblast, 5.7% less.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,717 | 745 | 140 |
| 10 | 11,433 | 1,490 | 280 |
| 15 | 17,150 | 2,235 | 420 |
Example: a 10 kW ground frame
For the loads of Kropyvnytskyi: 11.16 kWp, 18 panels, 372 kg of steel, 12 piles, materials ≈ 48,082 UAH.
How these numbers are computed
Nearby
- Holubenka4 km1,144 kWh/kWp
- Kalnybolota5 km1,143 kWh/kWp
- Pokrovka6 km1,142 kWh/kWp
- Pryyut6 km1,142 kWh/kWp
- Yampil6 km1,138 kWh/kWp
- Skalivski Khutory6 km1,144 kWh/kWp
All places: Holovanivskyi RaionKirovohrad Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.