Solar plant: site data

Solar power plant in Ternavka, Shepetivskyi Raion, Khmelnytskyi Oblast

Ternavka: 1,081 kWh per kWp a year, tilt 36° 1° east of south (PVGIS). 1.7% below the oblast median (1,100). #267 of 307 in the rayon, #1013 of 1109 in the oblast.

Shepetivka, the rayon centre, is 36 km away. 271 m above sea level. 22 km away: Iziaslav, the nearest bigger centre, 1,092 — 1.0% less here. Snow and wind from the nearest regional centre in the DBN — Хмельницький, 59 km. 11.74 m between rows, pitch 15.61 m (latitude 49.9°).

Yield of 1 kWp
1,081kWh/year
Tilt
36°1° east of south
10 kW
10,811kWh/year
Row pitch
15.61m · GCR 0.31
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,340 / 500Pa

Ground frame designer

A ground frame for a solar plant: Ternavka

The designer opens with this place’s coordinates, latitude 49.9° for the row spacing and the DBN loads of the nearest regional centre — Хмельницький, 59 km: snow 1,340 Pa, wind 500 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

27Jan46Feb83Mar118Apr134May137Jun140Jul138Aug112Sep83Oct37Nov28Dec

July: 140 kWh/kWp, January: 27 — 5.2 times less.

January: 27 against 32 in the oblast, 15.6% less.

Ternavka: plants, kWh
kWpA yearJulyJanuary
55,406700135
1010,8111,400270
1516,2162,100405

Snow and wind: Хмельницький

Example: a 10 kW ground frame

For the loads of Khmelnytskyi: 11.16 kWp, 18 panels, 415 kg of steel, 16 piles, materials ≈ 55,054 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Shepetivskyi RaionKhmelnytskyi Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.