Solar power plant in Mykytyntsi, Khmelnytskyi Raion, Khmelnytskyi Oblast

Mykytyntsi: 1,117 kWh per kWp a year, tilt 36° 2° east of south (PVGIS). 1.5% above the oblast median (1,100). #80 of 576 in the rayon, #265 of 1109 in the oblast.

Khmelnytskyi, the rayon centre, is 25 km away. 310 m above sea level. 21 km away: Derazhnya, the nearest bigger centre, the same 1,118. Snow and wind from the nearest regional centre in the DBN — Хмельницький, 24 km. 11.13 m between rows, pitch 15.00 m (latitude 49.2°).

Yield of 1 kWp
1,117kWh/year
Tilt
36°2° east of south
10 kW
11,171kWh/year
Row pitch
15.00m · GCR 0.32
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,340 / 500Pa

Ground frame designer

A ground frame for a solar plant: Mykytyntsi

The designer opens with this place’s coordinates, latitude 49.2° for the row spacing and the DBN loads of the nearest regional centre — Хмельницький, 24 km: snow 1,340 Pa, wind 500 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

34Jan54Feb90Mar118Apr135May139Jun140Jul139Aug114Sep85Oct38Nov31Dec

July: 140 kWh/kWp, December: 31 — 4.5 times less.

December: 31 against 29 in the oblast, 6.9% more.

Mykytyntsi: plants, kWh
kWpA yearJulyDecember
55,586700155
1011,1711,400310
1516,7572,100465

Snow and wind: Хмельницький

Example: a 10 kW ground frame

For the loads of Khmelnytskyi: 11.16 kWp, 18 panels, 415 kg of steel, 16 piles, materials ≈ 55,054 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Khmelnytskyi RaionKhmelnytskyi Oblast: rayons and towns

Free calculators

Sources