Solar plant: site data

Solar power plant in Kosohirka, Khmelnytskyi Raion, Khmelnytskyi Oblast

Kosohirka: 1,110 kWh per kWp a year, tilt 36° 2° east of south (PVGIS). 0.9% above the oblast median (1,100). #144 of 576 in the rayon, #374 of 1109 in the oblast.

Khmelnytskyi, the rayon centre, is 40 km away. 367 m above sea level. 12 km away: Yarmolyntsi, the nearest bigger centre, 1,100 — 0.9% more here. Snow and wind from the nearest regional centre in the DBN — Хмельницький, 40 km. 11.03 m between rows, pitch 14.90 m (latitude 49.1°).

Yield of 1 kWp
1,110kWh/year
Tilt
36°2° east of south
10 kW
11,096kWh/year
Row pitch
14.90m · GCR 0.32
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,340 / 500Pa

Ground frame designer

A ground frame for a solar plant: Kosohirka

The designer opens with this place’s coordinates, latitude 49.1° for the row spacing and the DBN loads of the nearest regional centre — Хмельницький, 40 km: snow 1,340 Pa, wind 500 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

32Jan50Feb87Mar118Apr134May138Jun141Jul139Aug115Sep85Oct38Nov32Dec

July: 141 kWh/kWp, January: 32 — 4.4 times less.

December: 32 against 29 in the oblast, 10.3% more.

Kosohirka: plants, kWh
kWpA yearJulyJanuary
55,548705160
1011,0961,410320
1516,6442,115480

Snow and wind: Хмельницький

Example: a 10 kW ground frame

For the loads of Khmelnytskyi: 11.16 kWp, 18 panels, 415 kg of steel, 16 piles, materials ≈ 55,054 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Khmelnytskyi RaionKhmelnytskyi Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.