Solar power plant in Hrechyntsi, Khmelnytskyi Raion, Khmelnytskyi Oblast

Hrechyntsi: 1,114 kWh per kWp a year, tilt 36° 3° east of south (PVGIS). 1.3% above the oblast median (1,100). #111 of 576 in the rayon, #320 of 1109 in the oblast.

Khmelnytskyi, the rayon centre, is 40 km away. 315 m above sea level. 14 km away: Stara Synyava, the nearest bigger centre, the same 1,109. Snow and wind from the nearest regional centre in the DBN — Хмельницький, 39 km. 11.35 m between rows, pitch 15.22 m (latitude 49.5°).

Yield of 1 kWp
1,114kWh/year
Tilt
36°3° east of south
10 kW
11,139kWh/year
Row pitch
15.22m · GCR 0.31
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,340 / 500Pa

Ground frame designer

A ground frame for a solar plant: Hrechyntsi

The designer opens with this place’s coordinates, latitude 49.5° for the row spacing and the DBN loads of the nearest regional centre — Хмельницький, 39 km: snow 1,340 Pa, wind 500 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

34Jan51Feb90Mar119Apr135May139Jun141Jul138Aug113Sep85Oct38Nov30Dec

July: 141 kWh/kWp, December: 30 — 4.7 times less.

January: 34 against 32 in the oblast, 6.3% more.

Hrechyntsi: plants, kWh
kWpA yearJulyDecember
55,570705150
1011,1391,410300
1516,7092,115450

Snow and wind: Хмельницький

Example: a 10 kW ground frame

For the loads of Khmelnytskyi: 11.16 kWp, 18 panels, 415 kg of steel, 16 piles, materials ≈ 55,054 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Khmelnytskyi RaionKhmelnytskyi Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.