Solar plant: site data
Solar power plant in Bronnyky, Shepetivskyi Raion, Khmelnytskyi Oblast
Bronnyky: 1,091 kWh per kWp a year, tilt 37° 1° east of south (PVGIS). 0.8% below the oblast median (1,100). #182 of 307 in the rayon, #794 of 1109 in the oblast.
Shepetivka, the rayon centre, is 19 km away. 242 m above sea level. 19 km away: Shepetivka, the nearest bigger centre, 1,085 — 0.5% more here. Snow and wind from the nearest regional centre in the DBN — Рівне, 77 km. 12.39 m between rows, pitch 16.21 m (latitude 50.3°).
- Yield of 1 kWp
- 1,091kWh/year
- Tilt
- 37°1° east of south
- 10 kW
- 10,910kWh/year
- Row pitch
- 16.21m · GCR 0.30
- T_min
- -40 °Cregion I, north-western
- Snow S₀ / wind W₀
- 1,320 / 520Pa
Ground frame designer
A ground frame for a solar plant: Bronnyky
The designer opens with this place’s coordinates, latitude 50.3° for the row spacing and the DBN loads of the nearest regional centre — Рівне, 77 km: snow 1,320 Pa, wind 520 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 137 kWh/kWp, December: 29 — 4.7 times less.
January: 36 against 32 in the oblast, 12.5% more.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,455 | 685 | 145 |
| 10 | 10,910 | 1,370 | 290 |
| 15 | 16,365 | 2,055 | 435 |
Example: a 10 kW ground frame
For the loads of Rivne: 11.16 kWp, 18 panels, 415 kg of steel, 16 piles, materials ≈ 55,054 UAH.
How these numbers are computed
Nearby
- Horodniavka3 km1,087 kWh/kWp
- Kruhlyk4 km1,103 kWh/kWp
- Senihiv5 km1,105 kWh/kWp
- Zamorochennia5 km1,102 kWh/kWp
- Chervonyi Tsvit5 km1,083 kWh/kWp
- Romaniv6 km1,096 kWh/kWp
All places: Shepetivskyi RaionKhmelnytskyi Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.