Solar plant: site data

Solar power plant in Slavne, Kakhovskyi Raion, Kherson Oblast

Slavne: 1,224 kWh per kWp a year, tilt 36° 3° east of south (PVGIS). 2.3% below the oblast median (1,253). #153 of 170 in the rayon, #593 of 711 in the oblast.

Nova Kakhovka, the rayon centre, is 61 km away. 64 m above sea level. 33 km away: Hornostayivka, the nearest bigger centre, 1,236 — 1.0% less here. Snow and wind from the nearest regional centre in the DBN — Херсон, 119 km. 9.49 m between rows, pitch 13.36 m (latitude 46.9°).

Yield of 1 kWp
1,224kWh/year
Tilt
36°3° east of south
10 kW
12,244kWh/year
Row pitch
13.36m · GCR 0.36
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
760 / 480Pa

Ground frame designer

A ground frame for a solar plant: Slavne

The designer opens with this place’s coordinates, latitude 46.9° for the row spacing and the DBN loads of the nearest regional centre — Херсон, 119 km: snow 760 Pa, wind 480 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

40Jan56Feb103Mar124Apr142May143Jun152Jul152Aug126Sep97Oct53Nov35Dec

July: 152 kWh/kWp, December: 35 — 4.3 times less.

January: 40 against 44 in the oblast, 9.1% less.

Slavne: plants, kWh
kWpA yearJulyDecember
56,122760175
1012,2441,520350
1518,3662,280525

Snow and wind: Херсон

Example: a 10 kW ground frame

For the loads of Kherson: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Kakhovskyi RaionKherson Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.