Solar plant: site data
Solar power plant in Novomykolaivka, Beryslavskyi Raion, Kherson Oblast
Novomykolaivka: 1,216 kWh per kWp a year, tilt 36° 3° east of south (PVGIS). 3.0% below the oblast median (1,253). #94 of 151 in the rayon, #648 of 711 in the oblast.
Beryslav, the rayon centre, is 56 km away. 79 m above sea level. 41 km away: Hornostayivka, the nearest bigger centre, 1,236 — 1.7% less here. Snow and wind from the nearest regional centre in the DBN — Херсон, 102 km. 9.77 m between rows, pitch 13.64 m (latitude 47.3°).
- Yield of 1 kWp
- 1,216kWh/year
- Tilt
- 36°3° east of south
- 10 kW
- 12,157kWh/year
- Row pitch
- 13.64m · GCR 0.35
- T_min
- -42 °Cregion II, south-eastern
- Snow S₀ / wind W₀
- 760 / 480Pa
Ground frame designer
A ground frame for a solar plant: Novomykolaivka
The designer opens with this place’s coordinates, latitude 47.3° for the row spacing and the DBN loads of the nearest regional centre — Херсон, 102 km: snow 760 Pa, wind 480 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 154 kWh/kWp, December: 33 — 4.7 times less.
January: 39 against 44 in the oblast, 11.4% less.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 6,079 | 770 | 165 |
| 10 | 12,157 | 1,540 | 330 |
| 15 | 18,236 | 2,310 | 495 |
Example: a 10 kW ground frame
For the loads of Kherson: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.
How these numbers are computed
Nearby
- Chereshneve4 km1,212 kWh/kWp
- Kostyrka7 km1,212 kWh/kWp
- Petropavlivka8 km1,220 kWh/kWp
- Novovoskresenske8 km1,220 kWh/kWp
- Blakytne9 km1,208 kWh/kWp
- Veremiivka9 km1,212 kWh/kWp
All places: Beryslavskyi RaionKherson Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.