Solar plant: site data

Solar power plant in Liubymivka, Henicheskyi Raion, Kherson Oblast

Liubymivka: 1,245 kWh per kWp a year, tilt 36° 2° east of south (PVGIS). 0.6% below the oblast median (1,253). #118 of 167 in the rayon, #442 of 711 in the oblast.

Henichesk, the rayon centre, is 48 km away. 33 m above sea level. 48 km away: Henichesk, the nearest bigger centre, 1,260 — 1.2% less here. Snow and wind from the nearest regional centre in the DBN — Херсон, 146 km. 9.29 m between rows, pitch 13.16 m (latitude 46.6°).

Yield of 1 kWp
1,245kWh/year
Tilt
36°2° east of south
10 kW
12,452kWh/year
Row pitch
13.16m · GCR 0.36
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
760 / 480Pa

Ground frame designer

A ground frame for a solar plant: Liubymivka

The designer opens with this place’s coordinates, latitude 46.6° for the row spacing and the DBN loads of the nearest regional centre — Херсон, 146 km: snow 760 Pa, wind 480 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

43Jan59Feb105Mar124Apr144May142Jun153Jul154Aug129Sep99Oct56Nov37Dec

August: 154 kWh/kWp, December: 37 — 4.2 times less.

January: 43 against 44 in the oblast, 2.3% less.

Liubymivka: plants, kWh
kWpA yearAugustDecember
56,226770185
1012,4521,540370
1518,6782,310555

Snow and wind: Херсон

Example: a 10 kW ground frame

For the loads of Kherson: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Henicheskyi RaionKherson Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.