Solar power plant in Kostomarove, Beryslavskyi Raion, Kherson Oblast

Kostomarove: 1,231 kWh per kWp a year, tilt 36° 3° east of south (PVGIS). 1.8% below the oblast median (1,253). #38 of 151 in the rayon, #536 of 711 in the oblast.

Beryslav, the rayon centre, is 26 km away. 63 m above sea level. 26 km away: Beryslav, the nearest bigger centre, the same 1,230. Snow and wind from the nearest regional centre in the DBN — Херсон, 64 km. 9.58 m between rows, pitch 13.45 m (latitude 47.0°).

Yield of 1 kWp
1,231kWh/year
Tilt
36°3° east of south
10 kW
12,309kWh/year
Row pitch
13.45m · GCR 0.36
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
760 / 480Pa

Ground frame designer

A ground frame for a solar plant: Kostomarove

The designer opens with this place’s coordinates, latitude 47.0° for the row spacing and the DBN loads of the nearest regional centre — Херсон, 64 km: snow 760 Pa, wind 480 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

41Jan57Feb104Mar125Apr142May143Jun152Jul152Aug128Sep98Oct52Nov36Dec

July: 152 kWh/kWp, December: 36 — 4.2 times less.

January: 41 against 44 in the oblast, 6.8% less.

Kostomarove: plants, kWh
kWpA yearJulyDecember
56,155760180
1012,3091,520360
1518,4642,280540

Snow and wind: Херсон

Example: a 10 kW ground frame

For the loads of Kherson: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Beryslavskyi RaionKherson Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.