Solar power plant in Hornostayivka, Kakhovskyi Raion, Kherson Oblast

Hornostayivka: 1,236 kWh per kWp a year, tilt 36° 1° east of south (PVGIS). 1.3% below the oblast median (1,253). #118 of 170 in the rayon, #495 of 711 in the oblast.

Nova Kakhovka, the rayon centre, is 40 km away. 82 m above sea level. 30 km away: Beryslav, the nearest bigger centre, the same 1,230. Snow and wind from the nearest regional centre in the DBN — Херсон, 94 km. 9.56 m between rows, pitch 13.43 m (latitude 47.0°).

Yield of 1 kWp
1,236kWh/year
Tilt
36°1° east of south
10 kW
12,363kWh/year
Row pitch
13.43m · GCR 0.36
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
760 / 480Pa

Ground frame designer

A ground frame for a solar plant: Hornostayivka

The designer opens with this place’s coordinates, latitude 47.0° for the row spacing and the DBN loads of the nearest regional centre — Херсон, 94 km: snow 760 Pa, wind 480 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

43Jan60Feb104Mar125Apr143May143Jun152Jul154Aug127Sep98Oct52Nov36Dec

August: 154 kWh/kWp, December: 36 — 4.3 times less.

November: 52 against 55 in the oblast, 5.5% less.

Hornostayivka: plants, kWh
kWpA yearAugustDecember
56,182770180
1012,3631,540360
1518,5452,310540

Snow and wind: Херсон

Example: a 10 kW ground frame

For the loads of Kherson: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Kakhovskyi RaionKherson Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.