Solar plant: site data

Solar power plant in Dobrosillia, Khersonskyi Raion, Kherson Oblast

Dobrosillia: 1,270 kWh per kWp a year, tilt 36° 2° east of south (PVGIS). 1.3% above the oblast median (1,253). #44 of 109 in the rayon, #231 of 711 in the oblast.

Kherson, the rayon centre, is 36 km away. 24 m above sea level. 29 km away: Oleshky, the nearest bigger centre, the same 1,264. Snow and wind from the nearest regional centre in the DBN — Херсон, 36 km. 9.23 m between rows, pitch 13.10 m (latitude 46.4°).

Yield of 1 kWp
1,270kWh/year
Tilt
36°2° east of south
10 kW
12,698kWh/year
Row pitch
13.10m · GCR 0.37
T_min
-42 °Cregion II, south-eastern
Snow S₀ / wind W₀
760 / 480Pa

Ground frame designer

A ground frame for a solar plant: Dobrosillia

The designer opens with this place’s coordinates, latitude 46.4° for the row spacing and the DBN loads of the nearest regional centre — Херсон, 36 km: snow 760 Pa, wind 480 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

47Jan64Feb109Mar129Apr143May143Jun155Jul154Aug131Sep99Oct56Nov39Dec

July: 155 kWh/kWp, December: 39 — 4.0 times less.

January: 47 against 44 in the oblast, 6.8% more.

Dobrosillia: plants, kWh
kWpA yearJulyDecember
56,349775195
1012,6981,550390
1519,0472,325585

Snow and wind: Херсон

Example: a 10 kW ground frame

For the loads of Kherson: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Khersonskyi RaionKherson Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.