Solar plant: site data
Solar power plant in Chulakivka, Skadovskyi Raion, Kherson Oblast
Chulakivka: 1,301 kWh per kWp a year, tilt 36° facing south (PVGIS). 3.8% above the oblast median (1,253). #69 of 114 in the rayon, #78 of 711 in the oblast.
Skadovsk, the rayon centre, is 51 km away. 14 m above sea level. 31 km away: Bilozerka, the nearest bigger centre, 1,286 — 1.2% more here. Snow and wind from the nearest regional centre in the DBN — Херсон, 37 km. 9.18 m between rows, pitch 13.05 m (latitude 46.4°).
- Yield of 1 kWp
- 1,301kWh/year
- Tilt
- 36°facing south
- 10 kW
- 13,009kWh/year
- Row pitch
- 13.05m · GCR 0.37
- T_min
- -42 °Cregion II, south-eastern
- Snow S₀ / wind W₀
- 760 / 480Pa
Ground frame designer
A ground frame for a solar plant: Chulakivka
The designer opens with this place’s coordinates, latitude 46.4° for the row spacing and the DBN loads of the nearest regional centre — Херсон, 37 km: snow 760 Pa, wind 480 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 157 kWh/kWp, December: 41 — 3.8 times less.
January: 50 against 44 in the oblast, 13.6% more.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 6,505 | 785 | 205 |
| 10 | 13,009 | 1,570 | 410 |
| 15 | 19,514 | 2,355 | 615 |
Example: a 10 kW ground frame
For the loads of Kherson: 11.16 kWp, 18 panels, 349 kg of steel, 12 piles, materials ≈ 47,980 UAH.
How these numbers are computed
Nearby
- Pamiatne10 km1,312 kWh/kWp
- Oleksiivka12 km1,329 kWh/kWp
- Zelenotropynske12 km1,306 kWh/kWp
- Zabaryne13 km1,292 kWh/kWp
- Sadove13 km1,322 kWh/kWp
- Novovolodymyrivka13 km1,311 kWh/kWp
All places: Skadovskyi RaionKherson Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.