Solar plant: site data
Solar power plant in Synykha, Kupianskyi Raion, Kharkiv Oblast
Synykha: 1,142 kWh per kWp a year, tilt 37° 1° east of south (PVGIS). Exactly the oblast median (1,142). #71 of 285 in the rayon, #866 of 1769 in the oblast.
Kupyansk, the rayon centre, is 21 km away. 101 m above sea level. 21 km away: Kupyansk, the nearest bigger centre, 1,150 — 0.7% less here. Snow and wind from the nearest regional centre in the DBN — Харків, 110 km. 11.66 m between rows, pitch 15.48 m (latitude 49.5°).
- Yield of 1 kWp
- 1,142kWh/year
- Tilt
- 37°1° east of south
- 10 kW
- 11,423kWh/year
- Row pitch
- 15.48m · GCR 0.31
- T_min
- -42 °Cregion II, south-eastern
- Snow S₀ / wind W₀
- 1,600 / 430Pa
Ground frame designer
A ground frame for a solar plant: Synykha
The designer opens with this place’s coordinates, latitude 49.5° for the row spacing and the DBN loads of the nearest regional centre — Харків, 110 km: snow 1,600 Pa, wind 430 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 147 kWh/kWp, December: 23 — 6.4 times less.
November: 38 against 40 in the oblast, 5.0% less.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,712 | 735 | 115 |
| 10 | 11,423 | 1,470 | 230 |
| 15 | 17,135 | 2,205 | 345 |
Example: a 10 kW ground frame
For the loads of Kharkiv: 11.16 kWp, 18 panels, 385 kg of steel, 12 piles, materials ≈ 51,876 UAH.
How these numbers are computed
Nearby
- Vorontsivka3 km1,149 kWh/kWp
- Bile5 km1,148 kWh/kWp
- Kushchuvakha6 km1,150 kWh/kWp
- Lisna Stinka7 km1,144 kWh/kWp
- Senok8 km1,148 kWh/kWp
- Senkove8 km1,141 kWh/kWp
All places: Kupianskyi RaionKharkiv Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.