Solar power plant in Malyi Kliuchiv, Kolomyiskyi Raion, Ivano-Frankivsk Oblast
Malyi Kliuchiv: 1,104 kWh per kWp a year, tilt 38° 3° east of south (PVGIS). 0.7% above the oblast median (1,097). #146 of 154 in the rayon, #242 of 700 in the oblast.
Kolomyia, the rayon centre, is 11 km away. 385 m above sea level. 11 km away: Kolomyia, the nearest bigger centre, 1,120 — 1.4% less here. Snow and wind from the nearest regional centre in the DBN — Івано-Франківськ, 52 km. 11.05 m between rows, pitch 14.82 m (latitude 48.5°).
- Yield of 1 kWp
- 1,104kWh/year
- Tilt
- 38°3° east of south
- 10 kW
- 11,043kWh/year
- Row pitch
- 14.82m · GCR 0.32
- T_min
- -38 °Cregion IIIA, Carpathian
- Snow S₀ / wind W₀
- 1,410 / 500Pa
Ground frame designer
A ground frame for a solar plant: Malyi Kliuchiv
The designer opens with this place’s coordinates, latitude 48.5° for the row spacing and the DBN loads of the nearest regional centre — Івано-Франківськ, 52 km: snow 1,410 Pa, wind 500 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 130 kWh/kWp, December: 42 — 3.1 times less.
December: 42 against 38 in the oblast, 10.5% more.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,522 | 650 | 210 |
| 10 | 11,043 | 1,300 | 420 |
| 15 | 16,565 | 1,950 | 630 |
Snow and wind: Івано-Франківськ
Example: a 10 kW ground frame
For the loads of Ivano-Frankivsk: 11.16 kWp, 18 panels, 410 kg of steel, 16 piles, materials ≈ 54,212 UAH.
How these numbers are computed
Nearby
- Velykyi Kliuchiv2 km1,104 kWh/kWp
- Runhury4 km1,096 kWh/kWp
- Pechenizhyn5 km1,102 kWh/kWp
- Myshyn6 km1,105 kWh/kWp
- Verkhnii Verbizh6 km1,106 kWh/kWp
- Markivka6 km1,085 kWh/kWp
All places: Kolomyiskyi RaionIvano-Frankivsk Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.