Solar plant: site data
Solar power plant in Krychka, Ivano-Frankivskyi Raion, Ivano-Frankivsk Oblast
Krychka: 1,072 kWh per kWp a year, tilt 39° 4° east of south (PVGIS). 2.3% below the oblast median (1,097). #233 of 244 in the rayon, #549 of 700 in the oblast.
Ivano-Frankivsk, the rayon centre, is 39 km away. 528 m above sea level — above 500 m the DBN snow and wind are higher. 18 km away: Nadvirna, the nearest bigger centre, 1,085 — 1.2% less here. Snow and wind from the nearest regional centre in the DBN — Івано-Франківськ, 39 km. 11.45 m between rows, pitch 15.17 m (latitude 48.7°).
- Yield of 1 kWp
- 1,072kWh/year
- Tilt
- 39°4° east of south
- 10 kW
- 10,719kWh/year
- Row pitch
- 15.17m · GCR 0.32
- T_min
- -38 °Cregion IIIA, Carpathian
- Snow S₀ / wind W₀
- 1,410 / 500Pa
Ground frame designer
A ground frame for a solar plant: Krychka
The designer opens with this place’s coordinates, latitude 48.7° for the row spacing and the DBN loads of the nearest regional centre — Івано-Франківськ, 39 km: snow 1,410 Pa, wind 500 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 122 kWh/kWp, December: 44 — 2.8 times less.
December: 44 against 38 in the oblast, 15.8% more.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,360 | 610 | 220 |
| 10 | 10,719 | 1,220 | 440 |
| 15 | 16,079 | 1,830 | 660 |
Snow and wind: Івано-Франківськ
Example: a 10 kW ground frame
For the loads of Ivano-Frankivsk: 11.16 kWp, 18 panels, 410 kg of steel, 16 piles, materials ≈ 54,212 UAH.
How these numbers are computed
Nearby
- Yablunka3 km1,073 kWh/kWp
- Maniava4 km1,055 kWh/kWp
- Lubenets4 km1,018 kWh/kWp
- Kryvets5 km1,075 kWh/kWp
- Boiky5 km1,050 kWh/kWp
- Rakovets6 km1,065 kWh/kWp
All places: Ivano-Frankivskyi RaionIvano-Frankivsk Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.