Solar power plant in Ávila, Spain: yield, tilt angle and row spacing

Ávila: 1,531 kWh per kWp a year at the optimal tilt of 35°, 4° east of south (PVGIS). 5.3% below the median of the main cities of Spain (1,615). #123 of 147 main cities of Spain by yield. For comparison, Kyiv: 1,114 kWh/kWp — 37.4% more here.

Ávila is in the province of Ávila, Castile and León. Population 57,657 (GeoNames). 1,127 m above sea level. 59 km away: Collado Villalba, the nearest bigger city, 1,582 kWh/kWp — 3.2% less here. 6.55 m between rows, pitch 10.47 m, GCR 0.46 (latitude 40.7°).

Yield of 1 kWp
1,531kWh/year
Tilt
35°4° east of south
10 kW
15,305kWh/year
Row pitch
10.47m · GCR 0.46
Rank in the country
123of 147 cities

Ground frame designer

A ground frame for a solar plant: Ávila

Latitude 40.7°: the tilt and the row pitch follow it. Enter the snow and wind for Spain in the designer, by the national annex to the Eurocode.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

88Jan100Feb128Mar135Apr151May153Jun170Jul166Aug144Sep122Oct86Nov88Dec

July: 170 kWh/kWp, November: 86 — 2.0 times less.

January: 88 against the median of 109 for the main cities of Spain, 19.3% less.

Ávila: plants, kWh
kWpA yearJulyNovember
57,653850430
1015,3051,700860
1522,9582,5501,290

Fixed tilt facing south

What a table yields at another tilt than the optimal 35° — for roofs and frames with a standard slope.

Ávila: yield at a fixed tilt, kWh/kWp
TiltA yearAgainst the optimum
35° (optimum)1,531—
15°1,460−4.6%
30°1,526−0.3%
45°1,513−1.2%
90°995−35.0%

Snow and wind loads

Snow and wind loads for a site in Spain follow CTE DB SE-AE (Spain’s Código Técnico de la Edificación) and, where the Eurocodes are applied, UNE-EN 1991-1-3 and UNE-EN 1991-1-4 with the Spanish National Annex. Solispec computes loads by the Ukrainian DBN V.1.2-2 only, so this page shows no snow or wind values for Spain: enter the characteristic values from these documents in the designer’s «Own snow S0» and «Own wind W0» fields.

The frame calculation for such a site is preliminary: before installation it must be checked by an engineer who works to the country’s standards.

Nearby cities

Spain: all cities and regions

Sources

Preliminary calculation: a design needs an engineer’s check.