Solar plant: site data

Solar power plant in Koshulyany, Dnistrovskyi Raion, Chernivtsi Oblast

Koshulyany: 1,157 kWh per kWp a year, tilt 37° facing south (PVGIS). 1.3% above the oblast median (1,143). #22 of 113 in the rayon, #86 of 422 in the oblast.

Kelmentsi, the rayon centre, is 32 km away. 115 m above sea level. 22 km away: Novoselytsya, the nearest bigger centre, the same 1,158. Snow and wind from the nearest regional centre in the DBN — Чернівці, 46 km. 10.63 m between rows, pitch 14.45 m (latitude 48.2°).

Yield of 1 kWp
1,157kWh/year
Tilt
37°facing south
10 kW
11,573kWh/year
Row pitch
14.45m · GCR 0.33
T_min
-38 °Cregion IIIA, Carpathian
Snow S₀ / wind W₀
1,320 / 500Pa

Ground frame designer

A ground frame for a solar plant: Koshulyany

The designer opens with this place’s coordinates, latitude 48.2° for the row spacing and the DBN loads of the nearest regional centre — Чернівці, 46 km: snow 1,320 Pa, wind 500 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

41Jan56Feb99Mar121Apr135May134Jun143Jul141Aug117Sep89Oct46Nov35Dec

July: 143 kWh/kWp, December: 35 — 4.1 times less.

January: 41 against 45 in the oblast, 8.9% less.

Koshulyany: plants, kWh
kWpA yearJulyDecember
55,787715175
1011,5731,430350
1517,3602,145525

Snow and wind: Чернівці

Example: a 10 kW ground frame

For the loads of Chernivtsi: 11.16 kWp, 18 panels, 412 kg of steel, 16 piles, materials ≈ 54,638 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Dnistrovskyi RaionChernivtsi Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.