Solar power plant in Berezhonka, Vyzhnytskyi Raion, Chernivtsi Oblast
Berezhonka: 1,107 kWh per kWp a year, tilt 37° 1° west of south (PVGIS). 3.1% below the oblast median (1,143). #39 of 94 in the rayon, #364 of 422 in the oblast.
Vyzhnytsya, the rayon centre, is 18 km away. 338 m above sea level. 18 km away: Vyzhnytsya, the nearest bigger centre, 1,076 — 2.8% more here. Snow and wind from the nearest regional centre in the DBN — Чернівці, 39 km. 10.67 m between rows, pitch 14.49 m (latitude 48.3°).
- Yield of 1 kWp
- 1,107kWh/year
- Tilt
- 37°1° west of south
- 10 kW
- 11,069kWh/year
- Row pitch
- 14.49m · GCR 0.33
- T_min
- -38 °Cregion IIIA, Carpathian
- Snow S₀ / wind W₀
- 1,320 / 500Pa
Ground frame designer
A ground frame for a solar plant: Berezhonka
The designer opens with this place’s coordinates, latitude 48.3° for the row spacing and the DBN loads of the nearest regional centre — Чернівці, 39 km: snow 1,320 Pa, wind 500 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 134 kWh/kWp, December: 31 — 4.3 times less.
December: 31 against 37 in the oblast, 16.2% less.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,535 | 670 | 155 |
| 10 | 11,069 | 1,340 | 310 |
| 15 | 16,604 | 2,010 | 465 |
Example: a 10 kW ground frame
For the loads of Chernivtsi: 11.16 kWp, 18 panels, 412 kg of steel, 16 piles, materials ≈ 54,638 UAH.
How these numbers are computed
Nearby
- Berezhnytsya4 km1,113 kWh/kWp
- Valy4 km1,096 kWh/kWp
- Karapchiv4 km1,136 kWh/kWp
- Korytne4 km1,132 kWh/kWp
- Maidan4 km1,128 kWh/kWp
- Seredniy Maydan5 km1,122 kWh/kWp
All places: Vyzhnytskyi RaionChernivtsi Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.