Solar power plant in Nosivka, Nizhynskyi Raion, Chernihiv Oblast
Nosivka: 1,124 kWh per kWp a year, tilt 38° 2° east of south (PVGIS). 1.5% above the oblast median (1,108). #8 of 327 in the rayon, #116 of 1558 in the oblast.
Nizhyn, the rayon centre, is 25 km away. 119 m above sea level. 25 km away: Nizhyn, the nearest bigger centre, 1,108 — 1.5% more here. Snow and wind from the nearest regional centre in the DBN — Чернігів, 65 km. 13.33 m between rows, pitch 17.10 m (latitude 50.9°).
- Yield of 1 kWp
- 1,124kWh/year
- Tilt
- 38°2° east of south
- 10 kW
- 11,243kWh/year
- Row pitch
- 17.10m · GCR 0.28
- T_min
- -40 °Cregion I, north-western
- Snow S₀ / wind W₀
- 1,720 / 410Pa
Ground frame designer
A ground frame for a solar plant: Nosivka
The designer opens with this place’s coordinates, latitude 50.9° for the row spacing and the DBN loads of the nearest regional centre — Чернігів, 65 km: snow 1,720 Pa, wind 410 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 145 kWh/kWp, December: 25 — 5.8 times less.
October: 79 against 75 in the oblast, 5.3% more.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,622 | 725 | 125 |
| 10 | 11,243 | 1,450 | 250 |
| 15 | 16,865 | 2,175 | 375 |
Example: a 10 kW ground frame
For the loads of Chernihiv: 11.16 kWp, 18 panels, 389 kg of steel, 12 piles, materials ≈ 52,358 UAH.
How these numbers are computed
Nearby
- Lukashivka5 km1,123 kWh/kWp
- Pidhaine5 km1,123 kWh/kWp
- Stavok7 km1,112 kWh/kWp
- Khutor Petrovo7 km1,124 kWh/kWp
- Debreve7 km1,122 kWh/kWp
- Andriivka8 km1,122 kWh/kWp
All places: Nizhynskyi RaionChernihiv Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.