Solar plant: site data

Solar power plant in Mudre, Prylutskyi Raion, Chernihiv Oblast

Mudre: 1,121 kWh per kWp a year, tilt 37° 3° east of south (PVGIS). 1.2% above the oblast median (1,108). #100 of 285 in the rayon, #217 of 1558 in the oblast.

Pryluky, the rayon centre, is 37 km away. 144 m above sea level. 37 km away: Pryluky, the nearest bigger centre, the same 1,116. Snow and wind from the nearest regional centre in the DBN — Черкаси, 113 km. 12.43 m between rows, pitch 16.25 m (latitude 50.4°).

Yield of 1 kWp
1,121kWh/year
Tilt
37°3° east of south
10 kW
11,214kWh/year
Row pitch
16.25m · GCR 0.29
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,520 / 420Pa

Ground frame designer

A ground frame for a solar plant: Mudre

The designer opens with this place’s coordinates, latitude 50.4° for the row spacing and the DBN loads of the nearest regional centre — Черкаси, 113 km: snow 1,520 Pa, wind 420 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

33Jan57Feb94Mar118Apr139May142Jun146Jul142Aug112Sep80Oct35Nov23Dec

July: 146 kWh/kWp, December: 23 — 6.3 times less.

October: 80 against 75 in the oblast, 6.7% more.

Mudre: plants, kWh
kWpA yearJulyDecember
55,607730115
1011,2141,460230
1516,8212,190345

Snow and wind: Черкаси

Example: a 10 kW ground frame

For the loads of Cherkasy: 11.16 kWp, 18 panels, 346 kg of steel, 12 piles, materials ≈ 51,820 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Prylutskyi RaionChernihiv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.