Solar power plant in Korop, Novhorod-Siverskyi Raion, Chernihiv Oblast

Korop: 1,105 kWh per kWp a year, tilt 38° 1° east of south (PVGIS). Exactly the oblast median (1,108). #34 of 247 in the rayon, #899 of 1558 in the oblast.

Novhorod-Siverskyi, the rayon centre, is 53 km away. 131 m above sea level. 41 km away: Konotop, the nearest bigger centre, the same 1,110. Snow and wind from the nearest regional centre in the DBN — Чернігів, 115 km. 14.06 m between rows, pitch 17.83 m (latitude 51.6°).

Yield of 1 kWp
1,105kWh/year
Tilt
38°1° east of south
10 kW
11,047kWh/year
Row pitch
17.83m · GCR 0.27
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,720 / 410Pa

Ground frame designer

A ground frame for a solar plant: Korop

The designer opens with this place’s coordinates, latitude 51.6° for the row spacing and the DBN loads of the nearest regional centre — Чернігів, 115 km: snow 1,720 Pa, wind 410 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

34Jan58Feb95Mar117Apr141May142Jun141Jul138Aug108Sep73Oct33Nov23Dec

June: 142 kWh/kWp, December: 23 — 6.2 times less.

December: 23 against 24 in the oblast, 4.2% less.

Korop: plants, kWh
kWpA yearJuneDecember
55,524710115
1011,0471,420230
1516,5712,130345

Snow and wind: Чернігів

Example: a 10 kW ground frame

For the loads of Chernihiv: 11.16 kWp, 18 panels, 389 kg of steel, 12 piles, materials ≈ 52,358 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Novhorod-Siverskyi RaionChernihiv Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.