Solar plant: site data
Solar power plant in Borzna, Nizhynskyi Raion, Chernihiv Oblast
Borzna: 1,115 kWh per kWp a year, tilt 38° 1° east of south (PVGIS). 0.6% above the oblast median (1,108). #134 of 327 in the rayon, #496 of 1558 in the oblast.
Nizhyn, the rayon centre, is 44 km away. 133 m above sea level. 44 km away: Nizhyn, the nearest bigger centre, 1,108 — 0.6% more here. Snow and wind from the nearest regional centre in the DBN — Чернігів, 83 km. 13.68 m between rows, pitch 17.45 m (latitude 51.3°).
- Yield of 1 kWp
- 1,115kWh/year
- Tilt
- 38°1° east of south
- 10 kW
- 11,146kWh/year
- Row pitch
- 17.45m · GCR 0.27
- T_min
- -40 °Cregion I, north-western
- Snow S₀ / wind W₀
- 1,720 / 410Pa
Ground frame designer
A ground frame for a solar plant: Borzna
The designer opens with this place’s coordinates, latitude 51.3° for the row spacing and the DBN loads of the nearest regional centre — Чернігів, 83 km: snow 1,720 Pa, wind 410 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
June: 143 kWh/kWp, December: 24 — 6.0 times less.
January: 34 against 35 in the oblast, 2.9% less.
| kWp | A year | June | December |
|---|---|---|---|
| 5 | 5,573 | 715 | 120 |
| 10 | 11,146 | 1,430 | 240 |
| 15 | 16,719 | 2,145 | 360 |
Example: a 10 kW ground frame
For the loads of Chernihiv: 11.16 kWp, 18 panels, 389 kg of steel, 12 piles, materials ≈ 52,358 UAH.
How these numbers are computed
Nearby
- Kynashivka4 km1,106 kWh/kWp
- Zabilivshchyna5 km1,107 kWh/kWp
- Zabilivshchyna Druha7 km1,106 kWh/kWp
- Liubomudrivka7 km1,113 kWh/kWp
- Malychyna Hreblia8 km1,102 kWh/kWp
- Zhdaniv8 km1,109 kWh/kWp
All places: Nizhynskyi RaionChernihiv Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.