Nechaieve: 1,143 kWh per kWp a year, tilt 36° 3° east of south (PVGIS). Exactly the oblast median (1,144). #86 of 197 in the rayon, #402 of 731 in the oblast.

Shpola, the rayon centre, is 22 km away. 160 m above sea level. 22 km away: Shpola, the nearest bigger centre, the same 1,144. Snow and wind from the nearest regional centre in the DBN — Кропивницький, 68 km. 10.81 m between rows, pitch 14.68 m (latitude 48.8°).

Yield of 1 kWp
1,143kWh/year
Tilt
36°3° east of south
10 kW
11,429kWh/year
Row pitch
14.68m · GCR 0.33
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,230 / 410Pa

Ground frame designer

A ground frame for a solar plant: Nechaieve

The designer opens with this place’s coordinates, latitude 48.8° for the row spacing and the DBN loads of the nearest regional centre — Кропивницький, 68 km: snow 1,230 Pa, wind 410 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

32Jan51Feb95Mar119Apr138May142Jun149Jul144Aug118Sep89Oct40Nov27Dec

July: 149 kWh/kWp, December: 27 — 5.5 times less.

January: 32 against 35 in the oblast, 8.6% less.

Nechaieve: plants, kWh
kWpA yearJulyDecember
55,715745135
1011,4291,490270
1517,1442,235405

Snow and wind: Кропивницький

Example: a 10 kW ground frame

For the loads of Kropyvnytskyi: 11.16 kWp, 18 panels, 382 kg of steel, 14 piles, materials ≈ 49,026 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Zvenyhorodskyi RaionCherkasy Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.