Solar plant: site data

Solar power plant in Hordashivka, Zvenyhorodskyi Raion, Cherkasy Oblast

Hordashivka: 1,139 kWh per kWp a year, tilt 36° 3° east of south (PVGIS). Exactly the oblast median (1,144). #150 of 197 in the rayon, #537 of 731 in the oblast.

Shpola, the rayon centre, is 55 km away. 176 m above sea level. 4 km away: Talne, the nearest bigger centre, the same 1,142. Snow and wind from the nearest regional centre in the DBN — Черкаси, 118 km. 10.88 m between rows, pitch 14.75 m (latitude 48.9°).

Yield of 1 kWp
1,139kWh/year
Tilt
36°3° east of south
10 kW
11,386kWh/year
Row pitch
14.75m · GCR 0.32
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,520 / 420Pa

Ground frame designer

A ground frame for a solar plant: Hordashivka

The designer opens with this place’s coordinates, latitude 48.9° for the row spacing and the DBN loads of the nearest regional centre — Черкаси, 118 km: snow 1,520 Pa, wind 420 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

36Jan51Feb90Mar118Apr139May142Jun148Jul144Aug116Sep88Oct40Nov28Dec

July: 148 kWh/kWp, December: 28 — 5.3 times less.

February: 51 against 55 in the oblast, 7.3% less.

Hordashivka: plants, kWh
kWpA yearJulyDecember
55,693740140
1011,3861,480280
1517,0792,220420

Snow and wind: Черкаси

Example: a 10 kW ground frame

For the loads of Cherkasy: 11.16 kWp, 18 panels, 346 kg of steel, 12 piles, materials ≈ 51,820 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Zvenyhorodskyi RaionCherkasy Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.