Solar plant: site data
Solar power plant in Stepove, Zviahelskyi Raion, Zhytomyr Oblast
Stepove: 1,105 kWh per kWp a year, tilt 37° 2° east of south (PVGIS). Exactly the oblast median (1,104). #65 of 294 in the rayon, #789 of 1700 in the oblast.
Zvyahel, the rayon centre, is 10 km away. 207 m above sea level. 10 km away: Zvyahel, the nearest bigger centre, the same 1,101. Snow and wind from the nearest regional centre in the DBN — Рівне, 86 km. 12.65 m between rows, pitch 16.47 m (latitude 50.6°).
- Yield of 1 kWp
- 1,105kWh/year
- Tilt
- 37°2° east of south
- 10 kW
- 11,054kWh/year
- Row pitch
- 16.47m · GCR 0.29
- T_min
- -40 °Cregion I, north-western
- Snow S₀ / wind W₀
- 1,320 / 520Pa
Ground frame designer
A ground frame for a solar plant: Stepove
The designer opens with this place’s coordinates, latitude 50.6° for the row spacing and the DBN loads of the nearest regional centre — Рівне, 86 km: snow 1,320 Pa, wind 520 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
June: 142 kWh/kWp, December: 27 — 5.3 times less.
January: 32 against 34 in the oblast, 5.9% less.
| kWp | A year | June | December |
|---|---|---|---|
| 5 | 5,527 | 710 | 135 |
| 10 | 11,054 | 1,420 | 270 |
| 15 | 16,581 | 2,130 | 405 |
Example: a 10 kW ground frame
For the loads of Rivne: 11.16 kWp, 18 panels, 415 kg of steel, 16 piles, materials ≈ 55,054 UAH.
How these numbers are computed
Nearby
- Pylypovychi3 km1,106 kWh/kWp
- Yarun3 km1,103 kWh/kWp
- Velykyi Molodkiv3 km1,108 kWh/kWp
- Pavlivka4 km1,101 kWh/kWp
- Hrud5 km1,103 kWh/kWp
- Horodyshche5 km1,100 kWh/kWp
All places: Zviahelskyi RaionZhytomyr Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.