Solar plant: site data

Solar power plant in Budne, Zhmerynskyi Raion, Vinnytsia Oblast

Budne: 1,146 kWh per kWp a year, tilt 36° 2° east of south (PVGIS). Exactly the oblast median (1,143). #42 of 151 in the rayon, #536 of 1206 in the oblast.

Zhmerynka, the rayon centre, is 36 km away. 218 m above sea level. 34 km away: Mohyliv-Podilskyy, the nearest bigger centre, 1,160 — 1.2% less here. Snow and wind from the nearest regional centre in the DBN — Вінниця, 66 km. 10.73 m between rows, pitch 14.60 m (latitude 48.7°).

Yield of 1 kWp
1,146kWh/year
Tilt
36°2° east of south
10 kW
11,455kWh/year
Row pitch
14.60m · GCR 0.33
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,360 / 470Pa

Ground frame designer

A ground frame for a solar plant: Budne

The designer opens with this place’s coordinates, latitude 48.7° for the row spacing and the DBN loads of the nearest regional centre — Вінниця, 66 km: snow 1,360 Pa, wind 470 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

34Jan52Feb90Mar122Apr140May141Jun144Jul143Aug117Sep88Oct42Nov32Dec

July: 144 kWh/kWp, December: 32 — 4.5 times less.

January: 34 against 36 in the oblast, 4.2% less.

Budne: plants, kWh
kWpA yearJulyDecember
55,728720160
1011,4551,440320
1517,1832,160480

Snow and wind: Вінниця

Example: a 10 kW ground frame

For the loads of Vinnytsia: 11.16 kWp, 18 panels, 346 kg of steel, 12 piles, materials ≈ 51,820 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Zhmerynskyi RaionVinnytsia Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.