Solar plant: site data

Solar power plant in Deptivka, Konotopskyi Raion, Sumy Oblast

Deptivka: 1,105 kWh per kWp a year, tilt 37° 2° east of south (PVGIS). Exactly the oblast median (1,110). #183 of 318 in the rayon, #1008 of 1534 in the oblast.

Konotop, the rayon centre, is 24 km away. 134 m above sea level. 24 km away: Konotop, the nearest bigger centre, the same 1,110. Snow and wind from the nearest regional centre in the DBN — Суми, 118 km. 13.12 m between rows, pitch 16.94 m (latitude 51.0°).

Yield of 1 kWp
1,105kWh/year
Tilt
37°2° east of south
10 kW
11,047kWh/year
Row pitch
16.94m · GCR 0.28
T_min
-40 °Cregion I, north-western
Snow S₀ / wind W₀
1,670 / 420Pa

Ground frame designer

A ground frame for a solar plant: Deptivka

The designer opens with this place’s coordinates, latitude 51.0° for the row spacing and the DBN loads of the nearest regional centre — Суми, 118 km: snow 1,670 Pa, wind 420 Pa.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Yield by month

33Jan55Feb91Mar115Apr140May144Jun143Jul140Aug109Sep77Oct35Nov22Dec

June: 144 kWh/kWp, December: 22 — 6.5 times less.

January: 33 against 36 in the oblast, 8.3% less.

Deptivka: plants, kWh
kWpA yearJuneDecember
55,524720110
1011,0471,440220
1516,5712,160330

Snow and wind: Суми

Example: a 10 kW ground frame

For the loads of Sumy: 11.16 kWp, 18 panels, 359 kg of steel, 12 piles, materials ≈ 53,991 UAH.

The whole frame: drawing, BOM, checks

How these numbers are computed

Nearby

All places: Konotopskyi RaionSumy Oblast: rayons and towns

Free calculators

Sources

Preliminary calculation: a design needs an engineer’s check.