Solar plant: site data
Solar power plant in Vlasivka, Berestynskyi Raion, Kharkiv Oblast
Vlasivka: 1,147 kWh per kWp a year, tilt 37° facing south (PVGIS). Exactly the oblast median (1,142). #149 of 208 in the rayon, #578 of 1769 in the oblast.
Berestyn, the rayon centre, is 26 km away. 121 m above sea level. 26 km away: Berestyn, the nearest bigger centre, 1,158 — 1.0% less here. Snow and wind from the nearest regional centre in the DBN — Харків, 68 km. 11.59 m between rows, pitch 15.41 m (latitude 49.5°).
- Yield of 1 kWp
- 1,147kWh/year
- Tilt
- 37°facing south
- 10 kW
- 11,468kWh/year
- Row pitch
- 15.41m · GCR 0.31
- T_min
- -42 °Cregion II, south-eastern
- Snow S₀ / wind W₀
- 1,600 / 430Pa
Ground frame designer
A ground frame for a solar plant: Vlasivka
The designer opens with this place’s coordinates, latitude 49.5° for the row spacing and the DBN loads of the nearest regional centre — Харків, 68 km: snow 1,600 Pa, wind 430 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 149 kWh/kWp, December: 24 — 6.2 times less.
November: 42 against 40 in the oblast, 5.0% more.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,734 | 745 | 120 |
| 10 | 11,468 | 1,490 | 240 |
| 15 | 17,202 | 2,235 | 360 |
Example: a 10 kW ground frame
For the loads of Kharkiv: 11.16 kWp, 18 panels, 359 kg of steel, 12 piles, materials ≈ 53,991 UAH.
How these numbers are computed
Nearby
- Shevchenkove2 km1,147 kWh/kWp
- Kofanivka2 km1,147 kWh/kWp
- Zolotukhivka3 km1,147 kWh/kWp
- Medvedivka5 km1,147 kWh/kWp
- Diachkivka6 km1,150 kWh/kWp
- Berezivka6 km1,142 kWh/kWp
All places: Berestynskyi RaionKharkiv Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.