Solar plant: site data
Solar power plant in Karabynivka, Pavlohradskyi Raion, Dnipropetrovsk Oblast
Karabynivka: 1,173 kWh per kWp a year, tilt 36° 2° east of south (PVGIS). Exactly the oblast median (1,177). #15 of 89 in the rayon, #991 of 1501 in the oblast.
Pavlohrad, the rayon centre, is 22 km away. 66 m above sea level. 22 km away: Pavlohrad, the nearest bigger centre, the same 1,172. Snow and wind from the nearest regional centre in the DBN — Дніпро, 43 km. 10.64 m between rows, pitch 14.51 m (latitude 48.6°).
- Yield of 1 kWp
- 1,173kWh/year
- Tilt
- 36°2° east of south
- 10 kW
- 11,733kWh/year
- Row pitch
- 14.51m · GCR 0.33
- T_min
- -42 °Cregion II, south-eastern
- Snow S₀ / wind W₀
- 1,340 / 470Pa
Ground frame designer
A ground frame for a solar plant: Karabynivka
The designer opens with this place’s coordinates, latitude 48.6° for the row spacing and the DBN loads of the nearest regional centre — Дніпро, 43 km: snow 1,340 Pa, wind 470 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 150 kWh/kWp, December: 28 — 5.4 times less.
January: 33 against 35 in the oblast, 5.7% less.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,867 | 750 | 140 |
| 10 | 11,733 | 1,500 | 280 |
| 15 | 17,600 | 2,250 | 420 |
Example: a 10 kW ground frame
For the loads of Dnipro: 11.16 kWp, 18 panels, 346 kg of steel, 12 piles, materials ≈ 51,820 UAH.
How these numbers are computed
Nearby
- Chervona Dolyna4 km1,173 kWh/kWp
- Novooleksandrivske4 km1,176 kWh/kWp
- Mineralni Vody5 km1,175 kWh/kWp
- Bulakhivka5 km1,168 kWh/kWp
- Novotroitske6 km1,175 kWh/kWp
- Lymanske8 km1,176 kWh/kWp
All places: Pavlohradskyi RaionDnipropetrovsk Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.