Solar power plant in Makiyivka, Nizhynskyi Raion, Chernihiv Oblast
Makiyivka: 1,114 kWh per kWp a year, tilt 37° 2° east of south (PVGIS). 0.5% above the oblast median (1,108). #153 of 327 in the rayon, #540 of 1558 in the oblast.
Nizhyn, the rayon centre, is 43 km away. 124 m above sea level. 40 km away: Pryluky, the nearest bigger centre, the same 1,116. Snow and wind from the nearest regional centre in the DBN — Київ, 95 km. 12.74 m between rows, pitch 16.56 m (latitude 50.7°).
- Yield of 1 kWp
- 1,114kWh/year
- Tilt
- 37°2° east of south
- 10 kW
- 11,135kWh/year
- Row pitch
- 16.56m · GCR 0.29
- T_min
- -40 °Cregion I, north-western
- Snow S₀ / wind W₀
- 1,550 / 370Pa
Ground frame designer
A ground frame for a solar plant: Makiyivka
The designer opens with this place’s coordinates, latitude 50.7° for the row spacing and the DBN loads of the nearest regional centre — Київ, 95 km: snow 1,550 Pa, wind 370 Pa.
- No sign-up
- Snow and wind check
- Drawings and estimate
Yield by month
July: 145 kWh/kWp, December: 25 — 5.8 times less.
February: 53 against 57 in the oblast, 7.0% less.
| kWp | A year | July | December |
|---|---|---|---|
| 5 | 5,568 | 725 | 125 |
| 10 | 11,135 | 1,450 | 250 |
| 15 | 16,703 | 2,175 | 375 |
Example: a 10 kW ground frame
For the loads of Kyiv: 11.16 kWp, 18 panels, 350 kg of steel, 12 piles, materials ≈ 49,237 UAH.
How these numbers are computed
Nearby
- Hannivka4 km1,114 kWh/kWp
- Pustotyne5 km1,116 kWh/kWp
- Ukrainka6 km1,116 kWh/kWp
- Stepove6 km1,114 kWh/kWp
- Verbove6 km1,114 kWh/kWp
- Klenove7 km1,114 kWh/kWp
All places: Nizhynskyi RaionChernihiv Oblast: rayons and towns
Free calculators
Sources
- PVGIS © European Union, 2001–2026 — yield, tilt and azimuth, data as of 2026-10-10
- GeoNames (CC BY 4.0) — coordinates, elevation and divisions (changed)
- DBN V.1.2-2:2006, DSTU-N B V.1.1-27:2010
- How these numbers are computed
Preliminary calculation: a design needs an engineer’s check.