Section of the table from the Solispec engine (Lutsk)

Ground plant · Lutsk

A 20 kW ground-mounted solar plant in Lutsk: structure, materials, cost

34 Ulica UL-620M-132DDGN (dual glass bifacial) panels (21.08 kW) on 1 table of 2 × 17. Snow and wind per the DBN for Lutsk: S₀ 1,240 Pa, W₀ 480 Pa.

Power
21.08kW
Steel
589.7kg
Posts
20
Bolts
230
Materials
86,208₴
Yield
22,661kWh/year

Ground frame designer

Design the 20 kW plant in the builder

Opens the 2 × 17 table with the Ulica UL-620M-132DDGN (dual glass bifacial) panel and the loads for Lutsk.

  • No sign-up
  • Snow and wind check
  • Drawings and estimate

Panel

Ulica UL-620M-132DDGN (dual glass bifacial): 620 W, 2,382 × 1,134 mm, portrait.

The table's structure

Layout1 table, each 2 × 17 = 34 panels
Loads (DBN V.1.2-2:2006)snow S₀ 1,240 Pa, wind W₀ 480 Pa, frost depth 0.9 m
PostsTube 60×60×2
RaftersC-channel 80×40×2
Purlins and bracesC-channel 60×40×2
Frames10 frames, pitch up to 2,120 mm
Posts20
Footings (bored concrete)20 pcs, Ø400 mm, depth 1,200 mm
Concrete3.32 m³
Tilt30°
Panel bottom / post top600 / 2,278 mm
Panel field size19,738 × 3,107 mm
Row spacing between tables (no shade on 21 December)12,620 mm at noon · 14,840 mm ±2 h
Steel589.7 kg
BoltsM10 — 158, M8 — 72
Panel clampsend 8, middle 64
Materials86,208 UAH
With installation and delivery139,868 UAH
Per 1 kW6,635 UAH/kW
Yield1,075 kWh/kW · 22,661 kWh/year

Checks and cautions

CheckValueStatus
Strength σ/fy94%with a caution
Deflection / (L/200)78%passes
Rafter strength86%with a caution
Post utilisation25%passes
Utilisation96%with a caution
Depth vs frost depthokpasses
  • Max. frame pitch, mmThe purlins between the frames are used above 80 % (strength or deflection): the structure passes, but the margin is small. A shorter frame pitch or a deeper purlin gives more margin.Frame spacing 2 120 mm, 10 frames. Purlin C-channel 60×40×2: strength 94%, deflection 78% of L/200 (snow on panel 797 Pa).
  • Rafter profileThe rafter is used above 80 %, or the frame's posts stand far apart: the structure passes, but the margin is small.Rafter C-channel 80×40×2: span between posts 2 276, cantilever 824 mm → strength 86%.
  • Embedment, mmThe footing resists wind uplift at above 80 % utilisation, or it is shallower than the frost depth. The soil resistance in the calculation is an estimate — check the soil on site.Foundation Ø400 × 1 200: 0.151 m³ of concrete per post. Wind uplift on the front post ≈ 14.0 kN (with γ=1.5) vs ≈ 14.6 kN (concrete weight + soil friction, estimate) → 96%.

Bill of materials

MarkPartProfileLength, mmQuantity
П1Front postTube 60×60×22,36510
П2Rear postTube 60×60×23,50310
Кр1Rafter (inclined beam)C-channel 80×40×23,92410
Пк1Frame strutC-channel 60×40×21,81110
Х1Longitudinal brace (cross)C-channel 60×40×22,6934
Р1Purlin (rail)C-channel 60×40×26,0002
Р2Purlin (rail)C-channel 60×40×26,0002
Р3Purlin (rail)C-channel 60×40×26,0002
Р4Purlin (rail)C-channel 60×40×26,0002
Р5Purlin (rail)C-channel 60×40×26,0002
Р6Purlin (rail)C-channel 60×40×26,0002
Р7Purlin (rail)C-channel 60×40×21,7382
Р8Purlin (rail)C-channel 60×40×21,7382
—Bolt M10×25 set · purlins, braces, connectors——50
—Bolt M10×90 set · strut to post — through spacer inserts——10
—Bolt M10×100 set · purlin to rafter——40
—Bolt M10×130 set · post–rafter — through spacer inserts——40
—Bolt M10×140 set · strut to rafter — through spacer inserts——10
—Bolt M10×150 set · brace to post — through spacer inserts——8
—End clamp 30 mm——8
—Mid clamp (30–40 mm)——64
—Bolt M8×50 + channel nut——72
—Concrete for 20 posts, Ø400×1200——3.32 m³

Profile cutting

39 bars of 6,000 mm, 205.8 m of profile in total.

  • Tube 60×60×210 bars
  • C-channel 80×40×210 bars
  • C-channel 60×40×219 bars

Estimated cost

Materials
86,208₴
With installation and delivery
139,868₴
Per 1 kW
6,635UAH/kW

The engine's estimate has 24 lines; the full list is in the builder. Prices are the typical market prices built into the Solispec engine, as of 06.10.2026; no margin, no VAT.

Yield

Yield: 1,075 kWh per 1 kW a year, ≈ 22,661 kWh a year in total for Lutsk (tilt 30°, the optimum for the latitude is 35.8°).

A preliminary calculation; a design needs an engineer's check. Snow and wind per DBN V.1.2-2:2006 for the regional centre; profiles, footings and estimate by the Solispec engine 0.12.0.